Bobbingworth Former Landfill Site

Aerial view of the site prior to works late 2006

  

Size: 8.95 hectares

 

Grid Reference: TL 53635 06505

Owners: Epping Forest District Council

Access: Currently there is no public  access to the site whilst restoration works are undertaken. Planned opening Spring 2010.

 

Bobbingworth Former Landlife Site is the name currently being used for this large, council owned site located to the south of Moreton village beside the Moreton Bridge Road.

 

During the 1950s the site was used for gravel extraction following which from 1961 to 1972 it was used  to take domestic rubbish. By 1974  the site had been filled and "restored" to green open space.

 

However, by the late 1980s there were indications that things were not as they should be and this prompted a second phase of restoration in 1989. Soil was imported from the Church Lane Flood Storage Reservoir (now one of EFDCs 9 local nature reserves) which was being created at the time. Some 200,000m³ of soil was imported and used to cap the site. Unfortunately, this may well have added to the problem as now leachate (polluted water) began to come out from the tip.

 

Through the 1990s numerous reports were written and solutions investigated, but it was not until 2004 that progress was finally made. Cleanaway (now Veolia) were awarded a contract by EFDC to remediate and restore the site and create a pocket park.

 

When the tip was filled in the 1960s recycling was non-exsistent. Consequently, newspapers, bottles, plastics and cans all went into the tip. During trial works in 2007 Newspaper from 1967 still readablemuch of this rubbish was revealed which dispite being in the ground nearly 40 years looked like it had been put there yesterday, as the newspaper opposite shows.

 

After detailed trials and investigation works Veolia decided apon a final solution and works finally began on site in 2007. Much of the soil imported from Church Lane has now been re-used to form an impermeable capping layer over the site, additional soil has also been imported to form a surface restoration layer to protect the engineered cap from the affects of weathering.

 

Along with capping, the site has also had a grout wall constructed to contain the leachate within the site.

 

giant machine used to dig the grout wall grout wall excavator
grout wall excavator The completed retaining grout wall

A treatment plant has also been built to improve the quality of the leachate before it is discharged into the adjacent sewerage treatment plant. A comprehensive network of drains has been installed from which leachate can be pumped as well as surface water drains that will feed a series of wetlands and ponds.

 

Poor weather in 2007 and the economic down turn in 2008 affected the importation of soil onto the site and the original timings have slipped. However, the final soil deliveries were completed in October 2008.

 

With the hard engineering completed the final phase of the project will be the testing of all the infrastructure and the landscaping which will be undertaken over the next few years. 

    

September 2008 - pond shortly after creation.

September 2008 - cascade of ponds are created

The Council's contractors Veolia will be managing and maintaining the site for the next seven years. During this time as well as ensuring the design is working they will be working closely with Countrycare in trying to create a biodiversity rescource with wetlands, a wildflower meadow, copses and hedegrows. In the winter 2008/09 the planting of over 4,500 trees is scheduled.

 

In partnership with Veolia, Countrycare will be organising volunteer projects on the site in the coming years. Full volunteering opportunities for the site are available in our walks, talks, events and volunteering page.

 

This website will be used to show the development of the site in the coming years so visit again for updates.

 

Timeline

 

  • November 2007 - First phase of landscaping starts as tree planting is undertaken. Over 1000 trees planted.
  • September 2008 - Second phase of landscaping starts with ponds being created.
  • October 2008 - Engineering works are completed.
  • November and December 2008 - Further tree planting takes place starting in National Tree Week. A further 4,500 trees are to be planted.

 

 

Contacting Us

Epping Forest District Council
Civic Offices
High Street
Epping
Essex CM16 4BZ
Main switchboard
(01992) 564000

Main email address
ContactUs@eppingforestdc.gov.uk